Spring is the most popular time of year to finish an extension, open up the back of a house or replace tired patio doors. As the evenings get lighter, homeowners want the kitchen to open onto the garden in time for Easter weekends and the first warm days.
The catch is that bespoke aluminium sliding doors and aluminium bifold doors are made to order. A spring installation is decided in winter, when the quoting, design and drawing sign-off happen. We’re already speaking to more homeowners planning for spring 2027, so this guide explains when to get in touch and how each stage fits together.
The short answer: If you’re aiming for a spring installation, get in touch in autumn or early winter. Allow around 8 to 12 weeks for manufacture from final drawing sign-off, plus time for the quote, your decision, design and installation. Factor in the two-week Christmas shutdown when planning your dates.

Work back from your spring date
The easiest way to plan is to choose the date you want the doors fitted and count backwards. This table assumes a replacement door or an opening that’s already built (see below if you’re building an extension).
| You want doors fitted in… | Make your first enquiry by… | Sign off final drawings by… |
|---|---|---|
| March 2027 | Enquire as early as possible and check availability. | Mid-December 2026 |
| April 2027 | Early December 2026 | Mid-January 2027 |
| May 2027 | Early January 2027 | Mid-February 2027 |
| June 2027 | Early February 2027 | Mid-March 2027 |
If you’re aiming for March or early April, the Christmas break is the main risk. There are fewer working weeks for design meetings and approvals, so the sooner your quote is in, the more slack you’ll have.
Why spring installation slots fill up
- Extensions reach the glazing stage together. Many builds start in late summer or autumn and are ready for their doors in spring, all at once.
- Production is scheduled in sign-off order. Each project joins the manufacturing schedule when its drawings are approved. If you sign off in February, you join the queue behind everyone who signed off in December and January.
- Christmas takes weeks out of the calendar. Fewer working days in December and early January push decisions back if they aren’t made in November.
- Everyone wants the same outcome. Most people want their doors open by the first warm weekend, so spring demand is concentrated into a few weeks.

How the process fits together: quotation to installation
Every bespoke sliding or bifold door project goes through the same six stages. Knowing which ones you control is the best way to protect your date.
1. Enquiry and quotation (around 1–2 weeks)
The more you send at the start, the more accurate the first quote and the fewer revisions later. Useful to include:
- Architect’s drawings or a sketch with approximate opening sizes
- Photos of the existing opening (for replacements)
- Whether you prefer sliding or bifold doors, or want advice
- Frame colour and any glass requirements (triple glazing, solar control, self-cleaning) Not sure? See double or triple glazing for bifold doors
- Your target installation date
The price depends on opening size, the number and size of panes, the system chosen, glass specification, frame finish, threshold detail, any automation, and site access for installation. For ballpark figures, see our price guide for sliding doors and how much aluminium patio doors cost.
2. Design development (around 2–4 weeks)
This is where the doors take shape. You choose the configuration (number of panes, which way they slide or fold, pocket doors, opening corners, bi-parting sliders) and the details that make a high-end installation look right:
- Sightlines: how slim the frames look when the doors are closed
- Threshold: a flush threshold needs the internal floor build-up and external levels agreed early (more in our guide to bifold doors with flush thresholds)
- Drainage and weathering: especially for exposed elevations and flush thresholds (see weather performance testing and ratings)
- Structure: your architect or engineer needs the weight of the doors and the allowable deflection of the steel or lintel above
Seeing the systems in person speeds decisions up a lot. You can book a showroom visit at our Amersham showroom to compare sliding and bifold doors side by side.
3. Survey and final dimensions
For a replacement, the existing opening is surveyed so the doors are made to the exact size.
For an extension or new build, the doors are often manufactured to the planned opening sizes in the approved drawings. Production can then run while your builder is still forming the opening, so the doors arrive when the structure is ready instead of weeks later. This only works if your builder keeps to the agreed dimensions and tolerances, so make sure they have the door drawings.
4. Drawing sign-off: when the clock starts
This is the most important date in the whole timeline. Manufacturing lead times are counted from the point your detailed drawings are approved and signed off, not from your first enquiry or your quote. Any change after sign-off (a different colour, an extra pane, a moved threshold level) can send the drawings back for revision and move your installation date.
To protect your spring date, make the big decisions before this point and sign off promptly.
5. Manufacturing (typically 8–12 weeks)
Each Sieger door is fabricated to your specification: thermally broken aluminium frames, powder-coated finish and glass units made to size. As a guide, our slim sliding door systems usually sit at the longer end of that range, and some bifold systems are shorter.
Things that can add time:
- Non-standard or dual colours
- Oversized or very heavy glass units
- Specialist glass such as heated or switchable privacy glass
- Automation for large sliding panes
6. Delivery and installation
Residential sliding door installation and bifold door installation lead times depend on the size and complexity of the project. Large or multi-pane installations, opening corners and automated systems can take longer. Very large glass panes may need lifting equipment and clear access from the road to the opening.
Before installation day, check that:
- the structural opening is complete, square and to the agreed size
- floor levels are set for the threshold detail
- there’s clear, safe access for the frames and glass
- power is in place if you’ve chosen automated sliders

Typical timeline at a glance
| Stage | Typical duration |
|---|---|
| Enquiry and quotation | 1–2 weeks |
| Design development and revisions | 2–4 weeks |
| Survey and drawing sign-off | 1–2 weeks |
| Manufacturing | 8–12 weeks |
| Delivery and installation | Depends on project size and complexity |
Building an extension? Add your builder’s timeline
In an extension, the glazing is usually on the critical path to making the building watertight. Late doors hold up everything after them: screed, plastering, kitchen fitting and decorating. Still at the design stage? Our guide to small glass extensions covers the glazing options.
- Bring us in at the design stage. Large sliding doors and bifolds affect the steelwork, the opening height and the floor build-up.
- Order to planned sizes so manufacturing overlaps with the build instead of starting after it.
- Agree a “ready for glazing” date with your builder and check it at every site meeting.
- Check planning and building regulations early. Replacing existing doors in a house is often permitted development, but new or enlarged openings, extensions, flats, listed buildings and properties in conservation areas may need planning permission. New openings need building control approval for the structure, and all new and replacement doors must meet current thermal requirements under Part L of the Building Regulations. Your local planning authority can confirm what applies to your property.
Bifold or sliding doors? Decide early
Choosing between bifold or sliding doors is the decision that most often slows down design. Settle it before you ask for detailed drawings.
- Sliding doors give larger panes of glass and slimmer frames, so you get the best view when the doors are closed, which in the UK is most of the year. The Sieger Slim Sliding Door has sightlines from 20mm and panes up to 2.5m wide by 3m tall. The Sieger Oversized Sliding Door can accommodate panels up to 4m wide or 4m high, depending on the specification, with triple glazing or laminated double glazing available.
- Bifold doors fold back to open almost the full width of the opening, which suits entertaining and indoor-outdoor living in summer. Slim systems such as the Sieger Lux Bifold 2.0 reduce the frame size you see when the doors are closed.
The choice also affects structure. Large sliding panes are heavy, and bifolds stack panes at one or both ends, so your engineer needs to know which you’re using. Still weighing up sliding doors vs bifold doors? Our guides on how to choose the right slim sliding doors and which bi-folding doors are best go into more detail.

Your spring door planning checklist
- Pick your target installation week and work back using the table above
- Send drawings, sizes and photos for a quotation
- Visit the showroom to decide between slimline sliding doors and bifolds
- Agree frame colour, glass specification and threshold detail
- Share the door drawings with your architect, engineer and builder
- Confirm whether your project needs planning permission or building control approval
- Use the table above as a guide and confirm your drawing sign-off date with us
- Confirm site readiness two weeks before installation
Already behind? What you can still do
If you’re reading this in January or February, you can still get your doors fitted in late spring or early summer:
- Get in touch to check which systems and installation dates are available..
- Make decisions in one go. Agree colour, glass and configuration in a single design meeting where possible.
- Stay with standard specifications where you can. Specialist finishes and glass usually add time.
- Ask about lead times for each system. Some systems are manufactured faster than others.
- Talk to your builder about temporary doors or boarding so other trades can carry on inside.
Frequently asked questions
What is the lead time for bifold doors?
Bespoke aluminium bifold doors usually take about 8–12 weeks to manufacture, counted from the date your final drawings are signed off. Allow another 4–8 weeks before that for quotation, design and survey.
How long does it take to install bifold or sliding doors?
Residential sliding and bifold door installation lead times depend on the size and complexity of the project. Large, multi-pane or automated systems can take longer.
When should I order doors for an extension finishing in spring?
At the design stage, ideally before building work starts. Ordering to planned opening sizes lets manufacturing run alongside the build, so the doors are ready when the opening is.
Do I need planning permission for bifold doors?
Replacing existing doors in a house is often covered by permitted development. New or enlarged openings, flats, listed buildings and homes in conservation areas may need permission, and all new doors must meet Building Regulations. Check with your local planning authority.
Can sliding or bifold doors be installed in winter?
Yes. Aluminium doors can be installed all year round. Booking a winter installation is one of the best ways to make sure your doors are in for the start of spring.
Why does drawing sign-off matter so much?
Manufacturing starts only when your detailed drawings are approved. Every week that sign-off slips usually moves your installation date by a week too.
Start planning your spring doors
If you’d like new sliding or bifold doors in place for spring, now is the time to start. Send us your drawings or opening sizes for a quotation, or book a visit to our Amersham showroom to see the Sieger range in person. We work with homeowners across London and the Home Counties, including bifold doors in London, Berkshire, Hertfordshire and Essex.